Minutes of the Banner Core Group Meeting, May 14, 1999
Buckman 358 1:20 – 2:25 p.m.

Attendees: Brother Kenneth Arnold, Susan Bittenbender, Craig Blackman, Lisa Chang, Carroll Keyes and Brother John McGoldrick

Absent: Tommy Faulkner, Barbara Havey, Cheryl Leslie, Ken Massa, Mary Ortiz and Rita Raniszewski

CC: President’s Council

New Items:

In order to meet the deadline of June 1, 1999, the Institutional Advancement Office (I.A.) and the Business Office (B.O.) will have to work very closely together with Brother Kenneth Arnold to convert I.A.’s organizations into Banner.

June 1, 1999 is a critical deadline because the Finance System is scheduled to go live. The organizations’ names and I.D. must be established in Banner so the Accounts Payable Department of the B.O. will be able to add the additional vendor information.

The organizations were originally scheduled to be converted by April 1999. However due to the FALA report and other extenuating circumstances, the conversion was not complete. According to Brother Kenneth Arnold, the conversion can be completed by June 1 if both I.A. and the B.O. focus their attention on the action items listed below:

Action Items:

1. Must be completed by Wednesday, May 19, 1999:

2. Must be completed by Friday, May 21, 1999: 3. Must be completed by Sunday, May 23, 1999: 4. Must be completed by Monday, June 1, 1999: ALERT: If the June 1, 1999 deadline is not met, the conversion of the Fundal data may be seriously jeopardized, because once the organizations are entered by the B.O., the I.A. will have to manually enter the rest of their information to prevent duplicates.
 
  1. Update on implementation of the Human Resources System

  2.  

     

    There was no report on the progress of this implementation.
     

  3. Update on implementation of the Finance System

  4.  

     

    There was no report on the progress of this implementation of the scheduled go-live date of June 1, 1999.
     

  5. Sybase Software (Carroll Keyes)

  6.  

     

    This software is installed and working satisfactorily for Sallie Mae to install the application for processing loans electronically. This test will be conducted when Steve Bellin, the Financial Aid Consultant, returns on June 14, 1999.
     

  7. Evision Printing demos (Carroll Keyes)
The Payroll Application to print payroll checks is installed and is ready for testing when the Human Resources Consultant, Bronwen Scott, returns on May 24, 1999.

Action Items:



Banner Home  | CBU Home